Law, professional codes and ethics are different
Think of them as three steps of a staircase. Each step is enforced by a different body and carries a different penalty. A professional can obey the law and still breach the code, and can obey the code and still act unethically.
1Law
What you must do. The enforceable minimum set by the state. Enforced by courts and authorities. Penalty: fines, licence loss, prosecution.
e.g. building without LDA-approved plans is illegal.
2Professional code
What your profession requires. Written, enforceable standard for members. Enforced by the regulator (PEC / PCATP). Penalty: reprimand, suspension, deregistration.
e.g. PEC Code of Conduct.
3Ethics
What you ought to do. Broadest standard of right conduct, often unwritten. Enforced by conscience and reputation. Applies "where rules go quiet".
e.g. speaking up about a colleague's shortcut.
Comparison table (draw this in the exam)
| Feature | Law | Professional code | Ethics |
|---|---|---|---|
| Question it answers | What must I do? | What does my profession require? | What ought I to do? |
| Set by | State / legislature | Regulatory body (PEC, PCATP) | Society, conscience, values |
| Written? | Yes — acts, bye-laws | Yes — code of conduct | Not always |
| Applies to | Everyone | Registered members only | Every person |
| Enforced by | Courts, authorities (LDA) | Disciplinary committee | Conscience, reputation |
| Penalty | Fine, prosecution, prison | Warning, suspension, licence revoked | Loss of trust, reputation |
| Level | Minimum | Middle | Highest |
Related: Code vs Contract (PEC vs FIDIC)
A single project always operates under both: a code governs the person; the contract governs the deal.
| PEC Code of Conduct | FIDIC Conditions of Contract | |
|---|---|---|
| Nature | Professional conduct standard | Standard-form contract terms |
| Applies to | Individual licensed engineers | Contracting parties (owner / contractor) |
| Focus | Integrity, competence, public safety | Risk allocation, payment, time, claims |
| Enforcement | PEC disciplinary proceedings | Dispute boards, arbitration, courts |
Practice
An engineer accepts an expensive gift from a supplier. No law was broken. Is there a problem? Explain using law, code and ethics.
Law: if no statute was broken, there may be no legal offence (though a gift linked to a decision could become bribery, which is a crime).
Code: yes — the PEC Code requires refusing gifts or favours that could influence decisions, and disclosing conflicts of interest. This is a disciplinary matter.
Ethics: yes — it compromises impartial judgment and fails the "newspaper test".
Conclusion: being legal does not make it professional or ethical. Law is only the minimum.
Give one example each of a breach of law, a breach of code, and a breach of ethics only.
- Law: constructing without LDA approval.
- Code: an engineer certifying a design outside their discipline (competence) — PEC can suspend them.
- Ethics only: staying silent about a colleague's unsafe shortcut that no rule specifically covers.
Short-answer questions
Define law in one line.
The enforceable minimum standard set by the state, enforced by courts and authorities.
Define a professional code of conduct.
A formal, written and enforceable standard of behaviour for members of a profession (e.g. PEC Code).
Define ethics.
A broader standard of right conduct — what you ought to do, even when no law or rule requires it.
Who enforces the PEC Code of Conduct?
The Pakistan Engineering Council, through disciplinary proceedings.
Name three penalties for breaching a professional code.
Reprimand/warning, suspension, deregistration (loss of licence).
Which of the three sets the minimum standard?
Law.
"A code governs the ___; the contract governs the ___."
Person; deal.
Give one example of an ethical duty not required by law.
Disclosing a conflict of interest nobody would otherwise discover.
Order of duties: public safety outranks the client's deadline
(rank 1)
However much pressure the deadline brings, the safety side is heavier.
Why this order?
- The public never signed the contract but pays the price if the building fails (Week 1: "the cost of getting it wrong is paid by people who never signed the contract").
- Your licence comes from the profession, so the code ranks above any one client.
- You owe the client loyalty and skill — but only within safety and the code.
- Personal gain is always last: it should never drive a professional decision.
Answer: Public safety (rank 1) outranks the client's deadline (rank 3). Do not sign. Offer solutions: request faster/accelerated testing, non-destructive tests, or adjust the programme. Record your decision in writing.
Real failures where this order was ignored
Rana Plaza, 2013 — 1,134 deaths
Cracks reported the day before; workers were still sent back in. Production deadline beat safety.
Hyatt Regency, 1981 — 114 deaths
A hanger-rod change was approved without recalculating the load. Engineers lost their licences for gross negligence.
Grenfell Tower, 2017 — 72 deaths
Combustible cladding specified and installed; warnings went unheeded.
Model answer structure (scenario questions)
- Identify the conflict: e.g. client deadline vs safety.
- Rank the duties using the 4-level order and say which one wins.
- Cite the principle: "public safety first" in the PEC Code.
- Give a practical action: stop/hold the work, inform the consultant, request tests.
- Document it: write it down — "a record protects you and the public".
Practice
Honeycombing is found in 2 of 12 basement columns. Your PM wants them patched with mortar tonight; handover is Friday. What do you do?
Correct option: hold work on those columns, inform the consultant, request tests (Option B in the Week 3 lab).
| Lens | A: Patch & carry on | B: Hold, inform, test |
|---|---|---|
| Consequences | Fails — hidden risk to occupants | Passes — short delay, risk managed |
| Duty & rights | Fails — breaches duty to report defects | Passes — meets code and contract notice duties |
| Fairness | Fails — client pays for a building they think is sound | Passes — everyone gets the same facts |
| Character | Fails the newspaper test | Passes — honest and defensible |
"Option B costs days. Option A can cost lives." Option C (patch but note privately) is still concealment. Option D (go straight to the regulator) skips the normal chain — escalate externally only if internal reporting fails.
Who signs off the slab? Owner's rep wants a Friday pour; the consultant's rebar inspection is Monday; the CM is on leave; the site engineer says the steel "looks fine".
- Authority: only the consultant (as named in the contract) can approve the reinforcement. The owner's rep and site engineer cannot override the inspection.
- Risk if it fails: the contractor (means and methods), plus the owner's rep for the instruction — and the public.
- Contractor should: refuse to pour without inspection, ask the consultant to bring the inspection forward, and confirm everything in writing.
- Duty at stake: public safety and competence; chain of authority.
Short-answer questions
List the order of duties from highest to lowest.
1 Public safety & law → 2 Profession & code → 3 Client & employer → 4 Personal gain.
Which ranks higher: the client or the profession's code?
The profession's code (rank 2 vs rank 3).
Why does public safety come first?
The public relies on the work but never signed the contract, and pays the price if it fails.
A deadline is a reason to ___ testing, never to ___ it.
Speed up (ask for faster testing); skip.
Rana Plaza (2013): how many died, and what was the human failure?
1,134. Cracks were reported the day before, but workers were sent back in.
Hyatt Regency (1981): what went wrong?
A hanger-rod connection change was approved without recalculating the load; 114 died.
Grenfell Tower (2017): what went wrong?
Combustible cladding was specified and installed and warnings were ignored; 72 died.
What should you always do after making a hard safety decision?
Write it down — a record protects you and the public.
Extension of time: owner delay and exceptional weather vs contractor delay
An Extension of Time (EOT) moves the completion date later. It protects the contractor from paying delay damages for days that were not its fault. Whether the contractor also gets money depends on who caused the delay.
| Cause of delay | Who controls it? | Extra time (EOT)? | Extra money? | Delay damages? |
|---|---|---|---|---|
| Owner delay (late drawings, late site access, late approvals, variations) | Owner | Yes | Yes — contractor's extra costs | No |
| Exceptional weather (neutral event) | Nobody | Yes | No | No |
| Contractor delay (poor planning, labour shortage, subcontractor default) | Contractor | No | No | Yes — contractor pays |
Why the rules work this way
- Owner delay: it would be unfair to punish the contractor for the owner's fault — and the owner should pay the cost it caused.
- Exceptional weather: nobody caused it, so the loss is shared — the contractor gets time (no penalty), the owner pays no extra money.
- Contractor delay: the contractor controls its own programme, so it carries that risk.
- Note: "exceptional" matters — normal seasonal rain is expected and should already be in the programme.
- Notice: under contracts like FIDIC, the contractor must notify delays and claims on time, or may lose the right to an EOT.
Worked example (Canal View Apartments)
The project finished 45 days late. Causes: 20 days owner late drawings, 10 days exceptional rain, 15 days contractor.
So the contractor pays damages for 15 days only — see Topic 4 for the money.
Practice
A project is 60 days late: 25 days owner variations, 5 days exceptional flood, 30 days contractor labour shortage. Find the EOT and culpable days.
EOT = 25 + 5 = 30 days. Contractor-culpable = 60 − 30 = 30 days. The contractor can also claim costs for the 25 owner days (not the 5 flood days).
Why does exceptional weather give time but not money?
Because neither party controls it. Giving time protects the contractor from damages; withholding money protects the owner. The risk is shared fairly between them.
Short-answer questions
What is an extension of time (EOT)?
A later completion date granted for delays the contractor did not cause, so it does not pay damages for them.
Owner delay gives the contractor what?
Time and money.
Exceptional weather gives the contractor what?
Time only — no extra cost.
Contractor delay gives the contractor what?
Nothing — it pays delay damages.
Give two examples of owner delay.
Late drawings; late site access (also late approvals or variations).
Does normal seasonal rain earn an EOT?
No — only exceptional weather. Normal rain should already be in the programme.
40 days late: 10 owner, 8 exceptional weather, 22 contractor. EOT?
10 + 8 = 18 days. Culpable = 22 days.
What can a contractor lose if it fails to notify a delay on time?
Its right to an extension of time (and related claims).
Delay damages: calculation and cap
Delay damages (also called liquidated damages, LDs) are a pre-agreed amount per day the contractor pays the owner for finishing late through its own fault. They are agreed in the contract so nobody has to prove the actual loss later. The cap limits the contractor's total exposure.
The 5-step method
- Split the delay by cause: owner / neutral (weather) / contractor.
- EOT = owner days + exceptional weather days.
- Culpable days = total delay − EOT.
- Daily rate in PKR = contract value × % per day. Damages = daily rate × culpable days.
- Cap = contract value × cap %. Contractor pays the lower of damages and cap.
Worked solution — Canal View (from the slides)
Contract PKR 600M; delay damages 0.1% per day, capped at 10%; 45 days late (20 owner, 10 rain, 15 contractor). Bonus: owner delay costs the contractor PKR 150,000 per day.
Green = 9M actually owed. The extension of time saves the contractor 18M, and the cap is never reached.
- Charging damages on all 45 days (that gives PKR 27M — wrong, ignores EOT).
- Giving the contractor money for the rain days — weather is time only.
- Forgetting to compare with the cap.
- Using 0.1 instead of 0.001 for 0.1%.
Try it: delay damages calculator
Practice
Contract PKR 400M, LDs 0.05%/day, cap 5%. 120 days late: 30 owner, 0 weather, 90 contractor. Find damages.
Daily rate = 0.05% × 400M = PKR 200,000. Damages = 200,000 × 90 = PKR 18M. Cap = 5% × 400M = PKR 20M. 18M < 20M → PKR 18M.
Same contract but 110 contractor days. What changes?
Damages = 200,000 × 110 = PKR 22M, which is above the cap of PKR 20M. Contractor pays PKR 20M (the cap applies).
Short-answer questions
Write the delay damages formula.
Damages = contract value × rate per day × culpable days (limited by the cap).
What is the purpose of the cap?
To limit the contractor's maximum exposure to delay damages.
Why are delay damages agreed in advance?
So the owner does not have to prove its actual loss later — it saves disputes.
0.1% of PKR 600M per day = ?
PKR 600,000 per day.
Cap of 10% on PKR 600M = ?
PKR 60M.
PKR 200M contract, 0.1%/day, 25 culpable days, cap 10%. Damages?
0.2M × 25 = PKR 5M (cap 20M not reached).
PKR 100M contract, 0.2%/day, 80 culpable days, cap 10%. Damages?
0.2M × 80 = 16M, but cap = 10M → PKR 10M.
If damages are below the cap, what does the contractor pay?
The calculated damages (always the lower of damages and cap).
Six principles of a code of conduct
| # | Principle | What the code demands | What it looks like on site |
|---|---|---|---|
| 1 | Public safety first | Safety, health and welfare of the public outrank client and employer interests | Stopping unsafe work even when the programme slips |
| 2 | Competence | Work only within your training and experience | Declining to certify a design outside your discipline |
| 3 | Honesty & integrity | No false statements and no concealment of defects | Accurate progress reports and test records |
| 4 | Conflict of interest | Disclose any interest that could bias your judgment | Declaring a family stake in a subcontractor |
| 5 | Confidentiality | Protect client information unless safety or law requires disclosure | Never sharing a rival's tender figures |
| 6 | Gifts & bribery | Refuse payments or favours that could influence decisions | Recording and declining a supplier's lavish gift |
What a code of conduct actually does (4 functions)
1Guides
Shows what good practice looks like before a crisis.
2Protects
Puts public safety and welfare ahead of private interest.
3Disciplines
Gives regulators a basis to sanction misconduct.
4Builds trust
Lets clients and society rely on a stranger's judgment.
Linked frameworks you can use in answers
Four ethical lenses
1 Consequences — most good, least harm? 2 Duty & rights — what do code, contract and law require? 3 Fairness — anyone favoured? 4 Character — could I explain it publicly (newspaper test)?
Five-step decision process
1 Get the facts → 2 Name stakeholders → 3 Check code and law → 4 Generate at least 3 options (incl. doing nothing) → 5 Test with the four lenses, decide, and record it.
Practice
A tile supplier sends a PKR 50,000 Eid hamper. Next week you approve their tile sample. Which option is best?
C — Decline politely and note the offer in the site diary.
- A (accept, say nothing) breaches gifts & bribery and honesty.
- B (accept, tell manager) is better but you still hold a gift that could influence the approval.
- D (accept, give to charity) — you still accepted it; the supplier's influence exists.
- C avoids the conflict and creates a written record. Principles: gifts & bribery, conflict of interest.
Which principle is breached: an engineer shares a rival bidder's price with a friendly contractor?
Confidentiality (and fairness / fair dealing). It is also bid manipulation — a potential corruption issue.
Short-answer questions
List the six principles of a code of conduct.
Public safety first, competence, honesty & integrity, conflict of interest, confidentiality, gifts & bribery.
Define competence.
Work only within your training and experience.
When may confidential client information be disclosed?
When safety or the law requires it.
Which principle: falsifying a cube test record?
Honesty and integrity.
Which principle: a structural engineer certifying an electrical design?
Competence.
Name the four functions of a code of conduct.
Guides, protects, disciplines, builds trust.
Name the four ethical lenses.
Consequences, duty & rights, fairness, character.
What is the "newspaper test"?
Asking whether you could comfortably explain your decision if it were published — the character lens.
List the five steps of ethical decision-making.
Get the facts, name stakeholders, check code and law, generate options, test and decide (and record it).
Regulators: PEC and PCATP
PEC — Pakistan Engineering Council
• Statutory body created under the PEC Act 1976
• Registers engineers (registration is required to practise as a professional engineer)
• Registers constructors / contractors by category and capacity — a contractor may only bid within its category limit
• Accredits engineering degree programmes
• Sets and enforces the PEC Code of Conduct (disciplinary proceedings)
PCATP — Pakistan Council of Architects & Town Planners
• Statutory body for architects and town planners
• Registers architects and town planners — an architect must be registered to practise
• Governs architectural practice and professional discipline
• Has its own code of conduct for members
The wider regulatory landscape
| Body | What it does | Why it matters on a project |
|---|---|---|
| PEC | Registers engineers & constructors, accredits engineering programmes, sets the Code of Conduct | Structural engineer and contractor need valid registration |
| PCATP | Registers architects and town planners | The architect must be registered to practise |
| HEC | Recognises degrees and universities | A degree opens the door — it is not a licence to practise |
| LDA | Approves plans and enforces building bye-laws in Lahore | No approval, no lawful construction |
| PPRA | Public procurement rules | Public-sector owners must follow PPRA tendering rules |
Why licensure exists
Formal licensure is one of the five marks of a profession (specialised knowledge, formal licensure, code of ethics, autonomy, accountability to the public). Entry is controlled by a regulator, not by the market alone, because the public cannot judge an engineer's competence by itself.
Consequences of misconduct
| Misconduct | Possible consequence |
|---|---|
| Practising without valid licensure | Regulatory penalties; work may be legally invalid |
| Breach of PEC / PCATP code | Reprimand, suspension or deregistration |
| Negligent design or supervision | Civil liability; professional indemnity claims |
| Bribery or corruption | Criminal prosecution; termination; blacklisting |
| Concealing known defects | Liability for failures; loss of professional standing |
Practice — "Who may do what?" (Week 4 activity)
| Situation | Verdict | Why |
|---|---|---|
| An unregistered architect signs the LDA submission | Not allowed | Only a PCATP-registered architect may practise and sign. |
| A fresh graduate supervises under a registered engineer | Allowed | Working under supervision is how graduates gain experience; the registered engineer stays responsible. |
| A contractor bids above its registered category limit | Not allowed | PEC registers contractors by category and capacity; bids must stay within the limit. |
| A firm lends its stamp to another firm for a fee | Not allowed | Misrepresentation and dishonesty — the stamp certifies work the firm did not do. A serious code breach. |
Explain the difference between HEC and PEC in one or two lines.
HEC recognises your degree (education). PEC registers you to practise and can discipline you. A degree alone does not let you sign engineering work.
Short-answer questions
What does PEC stand for?
Pakistan Engineering Council.
What does PCATP stand for?
Pakistan Council of Architects and Town Planners.
List three functions of PEC.
Registers engineers and constructors; accredits engineering programmes; sets and enforces the Code of Conduct.
How does PEC register contractors?
By category and capacity — each category has a contract value limit.
What is the role of LDA?
Approves building plans and enforces building bye-laws in Lahore.
What is the role of HEC?
Recognises degrees and universities.
Complete: "Education gets you in. Registration ___. Conduct ___."
Lets you sign; keeps you there.
Name the five marks of a profession.
Specialised knowledge, formal licensure, code of ethics, autonomy & judgment, accountability to the public.
What can happen if you practise without a valid licence?
Regulatory penalties, and the work may be legally invalid.
Contract Act 1872 checklist
| # | Element | Meaning | Construction example |
|---|---|---|---|
| 1 | Offer (proposal) | One party clearly states what it is willing to do, on what terms | Contractor submits a tender / bid |
| 2 | Acceptance | The other party agrees to the offer unconditionally; a changed acceptance is a counter-offer | Owner issues a letter of acceptance |
| 3 | Consideration | Something of value given by each side | Price paid ↔ work done |
| 4 | Free consent | Agreement not caused by coercion, undue influence, fraud, misrepresentation or mistake | No threats or false information to win the job |
| 5 | Lawful object | The purpose must not be illegal or against public policy | A contract to build without LDA approval, or one involving a bribe, is not enforceable |
| 6 | Capacity of parties | Parties must be of age, of sound mind and not legally disqualified; the signatory must have authority to bind the company | Check the signing officer is authorised by the firm |
❌ No direct contract between owner and subcontractor — the owner claims against the main contractor, who claims against the sub.
Practical points for construction
- Construction also needs a clear scope, price and time.
- Writing is not always required, but it is your best evidence.
- Check who has authority to bind the company.
- Privity of contract: only the parties to a contract can enforce it. The owner has no direct contract with subcontractors, so claims travel along the chain (owner → main contractor → subcontractor).
Scenario: the letter of intent (Week 5)
Model answer
- Full contract? Probably not for the whole works — key terms (final price, full scope) were "to follow", so acceptance of the full deal is incomplete.
- Limited contract? Arguably yes for mobilisation: the email is a clear instruction (offer), the contractor acted on it (acceptance by conduct), and the work had value (consideration).
- Claim: the contractor can claim its reasonable costs of the mobilisation it was asked to do (the PKR 18M, if reasonable and proven) — either under the limited contract or as payment for a non-gratuitous benefit (the idea behind s.70 of the Contract Act).
- Lesson: "A letter of intent can bind you, so cap what you spend on it." The LOI should state a spending limit and what happens if no contract follows.
A contractor is forced to sign under threat of losing an unrelated payment. Which element fails?
Free consent (coercion). The contract is voidable at the option of the party whose consent was not free.
Short-answer questions
Define a contract.
A promise (agreement) the law will enforce.
List the six essentials under the Contract Act 1872.
Offer, acceptance, consideration, free consent, lawful object, capacity of parties.
What is consideration?
Something of value exchanged by each party — e.g. price for work.
Name four things that destroy free consent.
Coercion, undue influence, fraud, misrepresentation (also mistake).
Who has capacity to contract?
A person of the age of majority, of sound mind and not disqualified by law (and, for a company, an authorised signatory).
An acceptance that changes the terms is called a ___.
Counter-offer.
Define privity of contract.
Only the parties to a contract can enforce it.
Can the owner sue a subcontractor directly under contract? Why?
Normally no — there is no contract between them (privity). Claims go through the main contractor.
Is a written contract always required?
Not always, but writing is the best evidence.
Key lesson from the letter-of-intent case?
A letter of intent can bind you, so cap what you spend on it.
Negligence: duty, breach, causation, damage
1Duty
Did the professional owe a duty of care? (e.g. a supervising engineer to the owner and to future occupants)
2Breach
Did they fall below the standard of care?
3Causation
Did that breach actually cause the loss?
4Damage
Is there real, measurable loss (repair cost, injury, delay)?
Role play: the weak concrete (Week 7)
Model answer using the four elements
- Duty: yes — the resident engineer was appointed to supervise quality on the owner's behalf.
- Breach: yes — all three cubes (average 19 MPa) are well below 25 MPa (about 24% short). A reasonable engineer would stop the next pour, report, and order further tests (cores) and a structural check. Signing off with no report is below the standard.
- Causation: yes — allowing floor 5 to be poured on a weak floor 4 caused the need for repair and strengthening of both.
- Damage: yes — repair and strengthening costs (PKR 85M in the slide problem).
- Verdict: likely negligence. The contractor also shares responsibility for supplying weak concrete (workmanship).
Who pays the loss? (worked calculation)
| Fact | Value |
|---|---|
| Repair and strengthening loss | PKR 85M |
| Responsibility — supervision consultant / contractor | 60% / 40% |
| Consultant fee | PKR 12M |
| Liability cap in consultant contract | 2 × fee |
| Professional indemnity (PI) insurance limit | PKR 50M per claim |
The consultant's 60% share was 51M, but the 2× fee cap cut it to 24M. The striped block is the loss the owner has to absorb.
What should the owner have negotiated at appointment? A higher liability cap (e.g. linked to the PI limit of PKR 50M or to the project value rather than 2× fee), proof of adequate PI insurance, and collateral warranties. With a PKR 50M cap the owner would recover 50M + 34M = 84M.
Try it: liability split calculator
A designer's beam fails because the contractor used the wrong steel grade. Is the designer negligent?
Probably not. The designer owed a duty, but if the design was correct there is no breach, and the loss was caused by the contractor's workmanship. Liability falls on the contractor (and possibly the supervisor if they should have checked the steel).
Short-answer questions
List the four elements of negligence.
Duty, breach, causation, damage.
Define standard of care.
What a reasonable professional of ordinary skill in the same field would do — not perfection.
Define causation.
The breach must have actually caused the loss.
If there is a breach but no loss, is there negligence?
No — damage is required.
Cubes 19, 20, 18 MPa vs 25 MPa specified. Average and shortfall?
Average 19 MPa — 6 MPa (24%) below specification.
What should the resident engineer have done with the weak cubes?
Stop the next pour, report in writing, order further tests (cores) and a structural check.
What is professional indemnity (PI) insurance?
Insurance that pays claims against a professional for negligent advice, design or supervision.
Fee PKR 10M, cap 3× fee, share PKR 40M, PI 50M. Consultant pays?
Cap = 30M → pays PKR 30M.
What should an owner negotiate at appointment to avoid a shortfall?
A higher liability cap and proof of adequate PI insurance.
Contract types and cost risk (lump sum, cost plus)
| Type | Price basis | Cost risk mainly with | Best used when |
|---|---|---|---|
| Lump sum | Fixed price for a defined scope | Contractor | Design is complete and scope is stable |
| Unit rate (BOQ) | Rates × measured quantities | Owner for quantity, contractor for rate | Quantities are uncertain |
| Cost plus | Actual cost + a fee | Owner | Scope is unclear and speed matters |
| Design build | One party designs and builds | Contractor for design and cost | Owner wants single-point responsibility |
Lump sum vs cost plus — side by side
Lump sum
Advantages (owner): price certainty, easy to compare bids, contractor motivated to be efficient.
Disadvantages: needs complete design; contractor adds a risk margin; every change becomes a variation claim; contractor may cut quality to protect profit.
Cost plus
Advantages: work can start before design is complete; flexible; open-book transparency.
Disadvantages: no price certainty for the owner; little incentive for the contractor to save cost; needs close auditing. Often controlled with a Guaranteed Maximum Price (GMP) or a target cost.
FIDIC standard forms
- Red Book — owner designs, contractor builds (usually measured / BOQ).
- Yellow Book — contractor designs and builds.
- Silver Book — turnkey (EPC); contractor carries most risk.
Delivery models (where the CM sits)
| Model | Owner contracts with | Where the CM sits | Watch out for |
|---|---|---|---|
| Design-Bid-Build | Designer, then contractor | Optional adviser | Gaps between design and build |
| Design-Build | One design-build firm | Owner's representative | Owner loses design control |
| CM as Agent | Designer, CM, trade contractors | Owner's agent, fee based | Owner holds the contract risk |
| CM at Risk | CM, who holds trade contracts | Guarantees a maximum price | Conflict: adviser and risk taker |
Practice
A hospital must open in 10 months but the design is only 30% complete. Which contract type would you recommend?
Cost plus with a guaranteed maximum price (or target cost). Scope is unclear and speed matters, so lump sum is unsuitable (no complete design). The GMP protects the owner from unlimited cost.
A simple warehouse with complete drawings and a fixed budget. Which type?
Lump sum. Design is complete and scope is stable, so the owner gets price certainty and the contractor can price the risk accurately.
Road earthworks where soil volumes are uncertain. Which type?
Unit rate (BOQ). Quantities are uncertain — the owner pays for actual measured quantities; the contractor carries the rate risk.
Short-answer questions
Define a lump sum contract.
A fixed price for a defined scope of work.
Define a cost plus contract.
The owner pays the actual cost plus a fee to the contractor.
Who carries cost risk in lump sum? In cost plus?
Lump sum: contractor. Cost plus: owner.
In a unit rate (BOQ) contract, who carries which risk?
Owner: quantity risk. Contractor: rate risk.
Give one disadvantage of cost plus for the owner.
No price certainty / little incentive for the contractor to save cost.
What is a GMP?
Guaranteed Maximum Price — a ceiling on cost, often added to cost plus or CM at Risk.
Name the FIDIC Red, Yellow and Silver Books.
Red: owner designs. Yellow: contractor designs. Silver: turnkey (EPC).
What is the main conflict in CM at Risk?
The CM is both the owner's adviser and a risk taker guaranteeing the price.
State the golden rule of risk allocation.
Give each risk to the party best able to control it, price it or insure it.
Who usually carries the risk of design errors and change in law?
The owner (for both).
Flashcards — key terms
Self-test quiz
Last-night revision sheet
1 · Law / Code / Ethics
Must → Required → Ought. Courts → Regulator → Conscience. Minimum → Middle → Highest.
2 · Order of duties
Public safety & law → Profession & code → Client & employer → Personal gain.
3 · Extension of time
Owner = time + money. Exceptional weather = time only. Contractor = no time, pays damages.
4 · Delay damages
Value × rate × culpable days; compare with cap; pay the lower. Canal View: 15 days × 0.6M = 9.0M (cap 60M).
5 · Six principles
Public safety · Competence · Honesty · Conflict of interest · Confidentiality · Gifts & bribery.
6 · Regulators
PEC: engineers, contractors (by category), accreditation, code. PCATP: architects & planners. HEC: degrees. LDA: approvals.
7 · Contract Act 1872
Offer · Acceptance · Consideration · Free consent · Lawful object · Capacity. Plus privity; LOIs can bind.
8 · Negligence
Duty · Breach · Causation · Damage. Standard = reasonable professional, not perfection. Weak concrete: owner recovers 58M of 85M.
9 · Contract types
Lump sum → contractor risk. BOQ → shared. Cost plus → owner risk. FIDIC Red / Yellow / Silver.
Answer-writing formula
Define the concept → Explain the rule/framework → Apply to the scenario → Conclude with a clear recommendation and "record it in writing".